SOLUTION: Phase I of the project consisted of three zones, namely, M1B3L2 (68 ha), M1B3L4 (108 ha) and M1B2L9 (176 ha)
- Coordination and supervision
- Pipe laying works
- Manholes chambers
- Construction and irrigation equipment set up
- Concrete Works
- Laying of drippers
- Testing/flushing of irrigation network
- Refurbishment of filtration plant, installation of PRV