SOLUTION: Phase I of the project consisted of three zones, namely, M1B3L2 (68 ha), M1B3L4 (108 ha) and M1B2L9 (176 ha)

  1. Coordination and supervision
  2. Pipe laying works
  3. Manholes chambers
  4. Construction and irrigation equipment set up
  5. Concrete Works
  6. Laying of drippers
  7. Testing/flushing of irrigation network
  8. Refurbishment of filtration plant, installation of PRV