Luxconsult gather relavant data, analyse and interpret it in the area of Baie du Tombeau for the purpose of sewarage in the year 2011 – 2012. The following task was conducted:-

  • Design of the reticulation network including pumping stations following hydraulic modelling using SewerCAD
  • Meetings with relevant concerned authorities
  • Identification of environmental impacts and mitigation measures
  • Preparation of an Environmental Management Plan
  • Preparation of an Environmental Monitoring Plan
  • Preparation of an EIA Report for obtention of the required EIA licence
  • Assistance in preparation of bid documents and evaluation of bids