Our Water Project
Conversion from high pressure sprinkler system to drip in the northern plain irrigation project: stage 1 (NPIP) – phase 1
Phase I of the project consisted of three zones, namely, M1B3L2 (68 ha), M1B3L4 (108 ha) and M1B2L9 (176 ha.
1.Coordination and supervision;
2.Pipe laying works;
3.Manholes chambers;
4.Construction and irrigation equipment set up;
5.Concrete Works;
6.Laying of drippers;
7.Testing/flushing of irrigation network;
8.Refurbishment of filtration plant, installation of PRV
From : 1998-2005